Much of the new AI data center capacity is being built with borrowed money. Alongside the largest tech companies, data center developers and companies that rent out AI chips are borrowing heavily. A handful of these borrowers hold most of the debt, and they pay very different interest rates. So we looked at who is borrowing, how much and on what terms.
Our analysts collected every debt financing of $500 million or more by 12 data center developers and GPU cloud companies from January 2025 through October 7, 2026, using SEC filings, company press releases and the SpaceX prospectus. For each one, we recorded how much the borrower raised, when, and at what interest rate. We also compared this borrowing with the bonds sold by Amazon, Alphabet, Meta and Oracle over the same period.
Debt financing here means bonds, convertible notes, term loans, construction loans and credit facilities. The 45 dollar-denominated instruments in the study total $131.28 billion, and CoreWeave alone raised 26.2% of it.
In the following sections, we total the debt by borrower and by quarter, compare interest rates, list every deal, and set the borrowing beside the hyperscalers' own bond offerings.
AI Data Center Debt Financing by Borrower
The AI Industry Reviews research team totaled the debt by borrower to show which data center developers and GPU cloud companies have borrowed the most to build AI capacity since the start of 2025.
The 45 dollar-denominated instruments total $131.28 billion. CoreWeave also sold EUR 2.00 billion of senior notes in June 2026, which is listed separately and left out of the dollar totals.
AI Data Center Debt by Borrower, January 2025 to October 7, 2026
| Borrower | Instruments | USD Total | Share of USD Total | Largest Single Instrument |
|---|---|---|---|---|
| CoreWeave | 12 | $34.34B plus EUR 2.00B | 26.2% | $8.50B term loan, Mar. 30, 2026 |
| Meta / Blue Owl | 1 | $27.30B | 20.8% | $27.30B senior secured notes, Oct. 16, 2025 |
| Nebius | 5 | $15.02B | 11.4% | $5.75B convertible notes, Aug. 24, 2026 |
| IREN | 5 | $9.90B | 7.5% | $3.00B convertible notes, May 14, 2026 |
| Crusoe | 2 | $7.85B | 6.0% | $7.10B construction loan, May 22, 2025 |
| TeraWulf | 5 | $7.03B | 5.4% | $3.20B senior secured notes, Oct. 23, 2025 |
| Vantage Data Centers | 3 | $7.00B | 5.3% | $2.75B credit facility, June 3, 2025 |
| Applied Digital | 3 | $6.09B | 4.6% | $2.35B senior secured notes, Nov. 20, 2025 |
| Cipher Mining | 4 | $5.84B | 4.5% | $2.00B senior secured notes, Feb. 11, 2026 |
| xAI (now part of SpaceX) | 3 | $5.00B | 3.8% | $3.00B senior secured notes, June 30, 2025 |
| Galaxy Digital | 2 | $4.91B | 3.7% | $3.51B senior secured notes, July 28, 2026 |
| Lambda | 1 | $1.00B | 0.8% | $1.00B credit facility, May 7, 2026 |
- CoreWeave raised $34.34 billion across 11 dollar instruments, 26.2% of the total. Its largest was an $8.50 billion delayed draw term loan in March 2026, priced at SOFR plus 2.25%.
- The $27.30 billion Hyperion bond is the largest single instrument in the set. It pays 6.581%, matures in May 2049 and was rated A+ by S&P, according to IFR. Meta's press release says PIMCO and other bond investors bought the notes in a private offering, with Morgan Stanley as sole bookrunner.
- Nebius raised $14.25 billion of its $15.02 billion through convertible notes, in four offerings of two series each.
- For investors, AI data center debt is concentrated in a few borrowers, which concentrates risk too. CoreWeave alone raised $34.34 billion, 26.2% of the total, and Meta's Hyperion bond was the largest single deal at $27.30 billion. Lenders' exposure will depend heavily on how these few companies perform.

AI Data Center Debt Financing by Quarter
Grouping the deals by quarter shows how quickly borrowing for AI data centers picked up and whether the pace has held in 2026.
Quarterly totals use the deal date in each filing or press release.
AI Data Center Debt by Quarter, 2025 to 2026
| Quarter | Instruments | USD Total | Largest Instrument |
|---|---|---|---|
| Q1 2025 | 0 | $0.00B | None found |
| Q2 2025 | 9 | $20.85B | Crusoe, $7.10B construction loan |
| Q3 2025 | 7 | $14.21B | Nebius, $3.16B convertible notes |
| Q4 2025 | 9 | $42.80B | Meta / Blue Owl, $27.30B senior secured notes |
| Q1 2026 | 5 | $17.49B | CoreWeave, $8.50B term loan |
| Q2 2026 | 9 | $17.10B | CoreWeave, $3.10B term loan |
| Q3 2026 | 6 | $18.83B | Nebius, $5.75B convertible notes |
- No deal of $500 million or more was disclosed in the first quarter of 2025. The first was Crusoe's $7.10 billion construction loan for phase 2 of its 1.2 gigawatt Abilene campus, announced May 22, 2025 and led by JPMorgan.
- The fourth quarter of 2025 was the largest, at $42.80 billion. Without the Hyperion bond, it would have been $15.50 billion.
- AI infrastructure borrowing has settled into a steady pace after a late-2025 spike. Each 2026 quarter came in between $17.10 billion and $18.83 billion, with $53.42 billion through October 7. If that pace holds, 2026 will end around $70 billion, below 2025's $77.86 billion.

AI Data Center Debt Financing Rates
The interest rate a borrower pays shows how much risk lenders see in it, and for AI data centers those rates vary widely from one borrower to the next.
Rates are the coupon on fixed-rate notes and the spread over SOFR, the US benchmark lending rate, on floating-rate loans. The construction loans and credit facilities from private borrowers did not disclose rates.
AI Data Center Debt by Instrument Type and Rate
| Instrument Type | Instruments | USD Total | Rate Range | Median Rate |
|---|---|---|---|---|
| Senior secured notes | 12 | $51.04B | 5.96% to 12.50% | 7.06% |
| Convertible notes | 12 | $30.66B | 0.00% to 4.50% (17 series) | 1.00% |
| Term loan | 11 | $25.98B | SOFR + 2.25% to SOFR + 7.25% (floating); 12.50% (one fixed loan) | SOFR + 4.125% |
| Construction loan | 2 | $9.35B | Not disclosed | Not disclosed |
| Senior unsecured notes | 5 (1 in euros, at 8.50%) | $7.75B | 9.00% to 9.75% | 9.44% |
| Credit facility | 4 | $6.50B | Not disclosed | Not disclosed |
- Senior secured notes were the most used tool by dollar volume, at $51.04 billion. Eleven of the 12 were sold by a subsidiary or joint venture set up for one data center project or one GPU fleet. All except the Hyperion notes, which run to 2049, mature five to six years after issue.
- The median secured note coupon fell from 7.50% across six deals in 2025 to 6.44% across six deals in 2026. The highest 2026 coupon was Galaxy Digital's 9.875% on its Helios notes in July.
- xAI paid the highest rates in the set: 12.50% on $3.00 billion of secured notes and a $1.00 billion fixed-rate loan, and SOFR plus 7.25% on a $1.00 billion floating-rate loan. The SpaceX prospectus says all three were repaid in March 2026 from a $20.00 billion SpaceX bridge loan, with a $518 million prepayment penalty on the notes.
- CoreWeave's term loan spreads ranged from SOFR plus 2.25% (March 2026) to SOFR plus 5.50% (August 2026). Its unsecured dollar notes paid 9.00% to 9.75%. Only xAI and Galaxy Digital paid more than 9.75% on secured notes.
- Borrowing costs for AI data centers are easing, but riskier borrowers still pay much more. The median secured note coupon fell from 7.50% in 2025 to 6.44% in 2026, while xAI paid up to 12.50%. If lenders stay confident, well-backed projects are likely to keep borrowing more cheaply.

AI Data Center Debt Financing Deal Table
Each financing has its own lenders, maturity and project, and seeing them one by one makes it easier to follow a single borrower's history.
Borrowing entities in parentheses are subsidiaries set up to hold a single project.
AI Data Center Debt Financing Deals, January 2025 to October 7, 2026
| Borrower | Date | Size | Instrument | Rate or Spread | Maturity |
|---|---|---|---|---|---|
| Crusoe, Blue Owl and Primary Digital Abilene joint venture | May 22, 2025 | $7.10B | Construction loan led by JPMorgan | Not disclosed | Not disclosed |
| CoreWeave | May 27, 2025 | $2.00B | 9.250% senior notes | 9.250% | June 2030 |
| Nebius Group | June 2, 2025 | $1.00B | 2.00% notes due 2029 and 3.00% notes due 2031 ($500M each) | 2.00% / 3.00% | 2029 / 2031 |
| Vantage Data Centers | June 3, 2025 | $2.25B | Green construction loan led by MUFG and Societe Generale | Not disclosed | Not disclosed |
| Vantage Data Centers | June 3, 2025 | $2.75B | Upsizing of green borrowing base loan to $5.75B | Not disclosed | Not disclosed |
| Crusoe | June 11, 2025 | $750M | Credit facility from Brookfield | Not disclosed | Not disclosed |
| xAI | June 30, 2025 | $3.00B | 12.5% senior secured notes | 12.50% | June 2030 |
| xAI | June 30, 2025 | $1.00B | Fixed-rate senior secured term loan | 12.50% | June 2030 |
| xAI | June 30, 2025 | $1.00B | Floating-rate senior secured term loan | SOFR + 7.25% | June 2030 |
| CoreWeave | July 25, 2025 | $1.75B | 9.000% senior notes | 9.000% | February 2031 |
| CoreWeave Compute Acquisition Co. VII (DDTL 3.0) | July 28, 2025 | $2.60B | Delayed draw term loan (DDTL 3.0) | SOFR + 4.00% | August 2030 |
| Galaxy Digital (Galaxy Helios I LLC) | Aug. 15, 2025 | $1.40B | Senior secured term loan | SOFR (2.50% floor) + 4.75% | August 2028 |
| TeraWulf | Aug. 20, 2025 | $1.00B | 1.00% convertible senior notes ($850M plus $150M option) | 1.00% | September 2031 |
| Nebius Group | Sept. 15, 2025 | $3.16B | 1.00% notes due 2030 and 2.75% notes due 2032 (approx. $1.58B each) | 1.00% / 2.75% | 2030 / 2032 |
| CoreWeave Compute Acquisition Co. IV (DDTL 2.0 upsizing) | Sept. 29, 2025 | $3.00B | Delayed draw term loan upsizing (DDTL 2.0) | SOFR + 4.25% | 5 years after each draw |
| Cipher Mining | Sept. 30, 2025 | $1.30B | 0.00% convertible senior notes | 0.00% | October 2031 |
| IREN | Oct. 14, 2025 | $1.00B | 0.00% convertible senior notes | 0.00% | July 2031 |
| Beignet Investor (Meta and Blue Owl Hyperion joint venture) | Oct. 16, 2025 | $27.30B | 6.581% senior secured amortizing notes, rated A+ by S&P | 6.581% (Treasuries + 225 bp) | May 2049 |
| TeraWulf (WULF Compute LLC) | Oct. 23, 2025 | $3.20B | 7.750% senior secured notes | 7.750% | October 2030 |
| TeraWulf | Oct. 31, 2025 | $1.02B | 0.00% convertible senior notes | 0.00% | May 2032 |
| Cipher Mining (Cipher Compute LLC) | Nov. 13, 2025 | $1.73B | 7.125% senior secured notes ($1.4B plus $333M add-on Nov. 24) | 7.125% | November 2030 |
| Applied Digital (APLD ComputeCo LLC) | Nov. 20, 2025 | $2.35B | 9.250% senior secured notes | 9.250% | December 2030 |
| IREN | Dec. 8, 2025 | $2.30B | 0.25% notes due 2032 and 1.00% notes due 2033 ($1.15B each) | 0.25% / 1.00% | 2032 / 2033 |
| CoreWeave | Dec. 11, 2025 | $2.59B | 1.75% convertible senior notes | 1.75% | December 2031 |
| TeraWulf (Flash Compute LLC) | Dec. 29, 2025 | $1.30B | 7.250% senior secured notes | 7.250% | December 2030 |
| Cipher Mining (Black Pearl Compute LLC) | Feb. 11, 2026 | $2.00B | 6.125% senior secured notes | 6.125% | February 2031 |
| Applied Digital (APLD ComputeCo 2 LLC) | Mar. 10, 2026 | $2.15B | 6.750% senior secured notes | 6.750% | March 2031 |
| TeraWulf (Raylan Data LLC) | Mar. 13, 2026 | $500M | 364-day delayed draw senior secured bridge facility | SOFR + 2.75% | 364 days |
| Nebius Group | Mar. 20, 2026 | $4.34B | 1.250% notes due 2031 ($2.5875B) and 2.625% notes due 2033 ($1.75B) | 1.250% / 2.625% | 2031 / 2033 |
| CoreWeave (DDTL 4.0) | Mar. 30, 2026 | $8.50B | Delayed draw term loan (DDTL 4.0) | SOFR + 2.25% | March 2032 |
| CoreWeave | Apr. 14, 2026 | $2.75B | 9.750% senior notes (incl. $1.0B add-on Apr. 21) | 9.750% | October 2031 |
| Lambda | May 7, 2026 | $1.00B | Senior secured credit facility (upsized from $275M) | Not disclosed | Not disclosed |
| IREN | May 14, 2026 | $3.00B | 1.00% convertible senior notes | 1.00% | December 2033 |
| CoreWeave (DDTL 5.0) | May 15, 2026 | $3.10B | Delayed draw term loan (DDTL 5.0) | SOFR + 4.50% | November 2031 |
| IREN (IE US Hardware 3 LLC) | May 29, 2026 | $2.10B | 5.96% senior notes, secured by the issuer's assets | 5.96% | December 2031 |
| IREN (IE US Hardware 3 LLC) | May 29, 2026 | $1.50B | Delayed draw term loan (approx.) | SOFR + 2.25% | December 2031 |
| Cipher Mining (Stingray Compute LLC) | June 15, 2026 | $810M | 6.000% senior secured notes | 6.000% | June 2031 |
| Applied Digital (APLD ComputeCo 3 LLC) | June 16, 2026 | $1.59B | 7.000% senior secured notes | 7.000% | June 2031 |
| CoreWeave | June 18, 2026 | $1.25B | 9.625% senior notes | 9.625% | July 2032 |
| CoreWeave | June 18, 2026 | EUR 2.00B | 8.500% euro senior notes | 8.500% | July 2032 |
| Nebius (subsidiaries) | July 17, 2026 | $775M | Senior secured term loan (approx.) | Term SOFR + 2.50% | October 2030 |
| Galaxy Digital (Galaxy Helios Data Centers II LLC) | July 28, 2026 | $3.51B | 9.875% senior secured notes, issued at 99.5% | 9.875% | August 2031 |
| CoreWeave (DDTL 5.5) | Aug. 7, 2026 | $2.60B | Delayed draw term loan (DDTL 5.5) | Term SOFR + 5.50% | September 2031 |
| Nebius Group | Aug. 24, 2026 | $5.75B | 0.50% notes due 2030 ($3.45B) and 4.50% notes due 2034 ($2.3B) | 0.50% / 4.50% | 2030 / 2034 |
| Vantage Data Centers | Sept. 14, 2026 | $2.00B | Five-year revolving development credit facility | Not disclosed | 5 years |
| CoreWeave | Sept. 22, 2026 | $4.20B | 2.875% convertible senior notes | 2.875% | 2033 |
Hyperscaler Bond Offerings, 2025 to 2026
Bond sales by the largest cloud companies give a sense of scale for the data center borrowing figures.
Amazon, Alphabet, Meta and Oracle also sold bonds in the same period. Each prospectus supplement says the money is for general corporate purposes, so this debt cannot be tied to data centers deal by deal. It is listed separately and kept out of the totals above. Microsoft filed no bond prospectus with the SEC from January 2025 to October 7, 2026.
Hyperscaler Bond Offerings by Company
| Company | USD Offerings | USD Total | Non-USD Offerings |
|---|---|---|---|
| Amazon | 3 | $77.00B | EUR 14.50B, CAD 14.00B, GBP 4.25B |
| Alphabet | 4 | $67.00B | EUR 6.75B, EUR 6.50B, GBP 4.50B, CAD 8.50B, EUR 9.00B, JPY 576.5B |
| Meta | 2 | $55.00B | None |
| Oracle | 3 | $50.75B | None |
Hyperscaler Bond Offerings, January 2025 to October 7, 2026
| Company | Pricing Date | Size | Tranches | Coupon Range | Maturities |
|---|---|---|---|---|---|
| Alphabet | Apr. 28, 2025 | $5.00B | 4 | 4.000% to 5.300% | 2030 to 2065 |
| Alphabet | Apr. 29, 2025 | EUR 6.75B | 5 | 2.500% to 4.000% | 2029 to 2054 |
| Alphabet | Nov. 3, 2025 | $17.00B | 7 | 3.875% to 5.700% | 2028 to 2075 |
| Alphabet | Nov. 3, 2025 | EUR 6.50B | 6 | 2.375% to 4.375% | 2028 to 2064 |
| Alphabet | Feb. 9, 2026 | $20.00B | 7 | 3.700% to 5.750% | 2029 to 2066 |
| Alphabet | Feb. 10, 2026 | GBP 4.50B | 4 | 4.125% to 5.875% | 2029 to 2058 |
| Alphabet | May 5, 2026 | CAD 8.50B | 4 | 3.650% to 5.000% | 2031 to 2056 |
| Alphabet | May 5, 2026 | EUR 9.00B | 6 | 3.200% to 4.800% | 2030 to 2063 |
| Alphabet | May 15, 2026 | JPY 576.5B | 7 | 1.965% to 4.599% | 2029 to 2066 |
| Alphabet | Aug. 6, 2026 | $25.00B | 10 | 4.500% to 6.500% plus two floating-rate tranches | 2028 to 2066 |
| Amazon | Nov. 17, 2025 | $15.00B | 6 | 3.900% to 5.550% | 2028 to 2065 |
| Amazon | Mar. 10, 2026 | $37.00B | 11 | 3.850% to 6.050% plus two floating-rate tranches | 2028 to 2076 |
| Amazon | Mar. 11, 2026 | EUR 14.50B | 8 | 2.800% to 4.850% plus one floating-rate tranche | 2028 to 2064 |
| Amazon | June 8, 2026 | CAD 14.00B | 5 | 3.400% to 5.000% | 2029 to 2056 |
| Amazon | July 7, 2026 | $25.00B | 8 | 4.600% to 6.250% plus one floating-rate tranche | 2029 to 2066 |
| Amazon | Sept. 9, 2026 | GBP 4.25B | 4 | 5.200% to 6.650% | 2029 to 2045 |
| Meta | Oct. 30, 2025 | $30.00B | 6 | 4.200% to 5.750% | 2030 to 2065 |
| Meta | Apr. 30, 2026 | $25.00B | 6 | 4.550% to 6.450% | 2031 to 2066 |
| Oracle | Jan. 30, 2025 | $7.75B | 6 | 4.800% to 6.125% plus one floating-rate tranche | 2028 to 2065 |
| Oracle | Sept. 24, 2025 | $18.00B | 6 | 4.450% to 6.100% | 2030 to 2065 |
| Oracle | Feb. 2, 2026 | $25.00B | 8 | 4.550% to 6.850% plus one floating-rate tranche | 2029 to 2066 |
- The four companies sold $249.75 billion of dollar bonds in 12 offerings, 1.9 times the $131.28 billion raised by the AI borrowers above.
- Amazon's $37.00 billion offering on March 10, 2026, in 11 tranches, was the largest single offering, $9.70 billion more than the Hyperion bond.
- Alphabet sold bonds in five currencies: dollars, euros, pounds, Canadian dollars and yen. Its yen offering totaled JPY 576.5 billion.
- Hyperscalers can borrow far more, and more cheaply, than the specialist AI firms they compete with. The four sold $249.75 billion of dollar bonds, 1.9 times what the AI borrowers raised. That gap is likely to keep favoring the largest cloud companies in the race to build capacity.
What AI Data Center Debt Financing Trends Mean for 2027 and Beyond
A large part of the AI data center boom is being paid for with borrowed money. A handful of companies have taken on most of it, so the health of the buildout rests on a few balance sheets, and the borrowers with weaker credit pay much higher interest to get it.
The debt only works if customers keep renting the computing capacity it pays for. If AI demand slows, the companies that borrowed the most at the highest rates would struggle first, and lenders would grow more cautious with everyone else. If demand holds, borrowing costs could keep easing and more projects could get funded.
So if you hold bonds or shares in AI infrastructure companies, check how much each one has borrowed and at what rate, because those numbers decide who gets through a slowdown.
Data Collection and Methodology
The deal list follows a few rules about size, sources and currency that are worth knowing before quoting any total.
The set includes each financing of $500 million or more that a company filing or press release confirms. For publicly traded borrowers (CoreWeave, Nebius, IREN, TeraWulf, Applied Digital, Cipher Mining and Galaxy Digital), the source is the Form 8-K or Form 6-K report filed with the SEC when each deal closed or priced. For private borrowers, the sources are press releases from Crusoe, Vantage Data Centers, Lambda and Newmark, the broker on Crusoe's Abilene, Texas loan. xAI's debt comes from the June 2026 SpaceX prospectus, filed after SpaceX acquired xAI. The Hyperion bond sold by Beignet Investor, a joint venture of Meta and funds managed by Blue Owl Capital, comes from Meta's press release and IFR.
The 46 debt deals come from 12 borrower groups, and 21 bond offerings by Amazon, Alphabet, Meta and Oracle are shown separately for comparison. Dates are the day a deal priced, closed or was announced, whichever the source gives first. Amounts are the committed or issued size, including any upsizing announced in the same filing. Figures are as of October 8, 2026.
The set covers deals of $500 million or more that a borrower or arranger disclosed. Private loans that were reported only in the press are left out, as are corporate revolving credit lines, Galaxy Digital's general-purpose exchangeable notes and equity sales such as at-the-market programs. Instrument sizes are commitments, and delayed draw loans may not be fully drawn. Non-dollar amounts are not converted. Six of the 46 instruments have no disclosed rate. The SpaceX prospectus gives June 2025 as the issue month for xAI's debt, so it is dated June 30, 2025 here, and the SpaceX bridge loan is left out because it refinanced debt across SpaceX.
Sources
- AI Industry Reviews, AI Data Center Debt Financing Study: analysis of 46 debt financings of $500 million or more by 12 AI data center and GPU cloud borrowers and 21 hyperscaler bond offerings, January 2025 to October 2026, from SEC filings and company press releases, conducted October 2026.
- Applied Digital, Form 8-K, senior secured notes, Nov. 20, 2025. https://www.sec.gov/Archives/edgar/data/1144879/000149315225024479/form8-k.htm
- Applied Digital, Form 8-K, senior secured notes, Mar. 10, 2026. https://www.sec.gov/Archives/edgar/data/1144879/000149315226009538/form8-k.htm
- Applied Digital, Form 8-K, senior secured notes, June 16, 2026. https://www.sec.gov/Archives/edgar/data/1144879/000149315226028899/form8-k.htm
- Cipher Mining, Form 8-K, convertible notes, Sept. 30, 2025. https://www.sec.gov/Archives/edgar/data/1819989/000119312525225645/d52925d8k.htm
- Cipher Mining, Form 8-K, senior secured notes, Nov. 13, 2025. https://www.sec.gov/Archives/edgar/data/1819989/000095010325014692/dp237330_8k.htm
- Cipher Mining, Form 8-K, senior secured notes, Nov. 13, 2025. https://www.sec.gov/Archives/edgar/data/1819989/000095010325015181/dp237816_8k.htm
- Cipher Mining, Form 8-K, senior secured notes, Feb. 11, 2026. https://www.sec.gov/Archives/edgar/data/1819989/000095010326001966/dp241421_8k.htm
- Cipher Mining, Form 8-K, senior secured notes, June 15, 2026. https://www.sec.gov/Archives/edgar/data/1819989/000095010326008994/dp248453_8k.htm
- CoreWeave, Form 8-K, senior unsecured notes, May 27, 2025. https://www.sec.gov/Archives/edgar/data/1769628/000176962825000025/crwv-20250527.htm
- CoreWeave, Form 8-K, senior unsecured notes, July 25, 2025. https://www.sec.gov/Archives/edgar/data/1769628/000119312525165924/d73657d8k.htm
- CoreWeave, Form 8-K, term loan, July 28, 2025. https://www.sec.gov/Archives/edgar/data/1769628/000176962825000033/crwv-20250728.htm
- CoreWeave, Form 8-K, term loan, Sept. 29, 2025. https://www.sec.gov/Archives/edgar/data/1769628/000119312525227562/d910811d8k.htm
- CoreWeave, Form 8-K, convertible notes, Dec. 11, 2025. https://www.sec.gov/Archives/edgar/data/1769628/000176962825000105/crwv-20251208.htm
- CoreWeave, Form 8-K, term loan, Mar. 30, 2026. https://www.sec.gov/Archives/edgar/data/1769628/000176962826000129/crwv-20260330.htm
- CoreWeave, Form 8-K, senior unsecured notes, Apr. 14, 2026. https://www.sec.gov/Archives/edgar/data/1769628/000176962826000164/crwv-20260409.htm
- CoreWeave, Form 8-K, senior unsecured notes, Apr. 14, 2026. https://www.sec.gov/Archives/edgar/data/1769628/000176962826000183/crwv-20260416.htm
- CoreWeave, Form 8-K, term loan, May 15, 2026. https://www.sec.gov/Archives/edgar/data/1769628/000176962826000236/crwv-20260515.htm
- CoreWeave, Form 8-K, senior unsecured notes, June 18, 2026. https://www.sec.gov/Archives/edgar/data/1769628/000176962826000291/crwv-20260618.htm
- CoreWeave, Form 8-K, term loan, Aug. 7, 2026. https://www.sec.gov/Archives/edgar/data/1769628/000176962826000357/crwv-20260807.htm
- CoreWeave, Form 8-K, convertible notes, Sept. 22, 2026. https://www.sec.gov/Archives/edgar/data/1769628/000176962826000432/crwv-20260917.htm
- Newmark, press release on $7.1 billion construction loan for Abilene AI data center, May 2025. https://www.prnewswire.com/news-releases/newmark-facilitates-7-1-billion-construction-loan-to-develop-ai-data-center-302463532.html
- Crusoe, press release on $750 million credit facility from Brookfield, June 2025. https://www.crusoe.ai/resources/newsroom/crusoe-secures-usd750-million-credit-facility-from-brookfield-to-accelerate
- Galaxy Digital, Form 8-K, term loan, Aug. 15, 2025. https://www.sec.gov/Archives/edgar/data/1859392/000185939225000039/glxy-20250815.htm
- Galaxy Digital, Form 8-K, senior secured notes, July 28, 2026. https://www.sec.gov/Archives/edgar/data/1859392/000185939226000079/glxy-20260728.htm
- IREN, Form 8-K, convertible notes, Oct. 14, 2025. https://www.sec.gov/Archives/edgar/data/1878848/000114036125038083/ef20056955_8k.htm
- IREN, Form 8-K, convertible notes, Dec. 8, 2025. https://www.sec.gov/Archives/edgar/data/1878848/000114036125044888/ef20060782_8k.htm
- IREN, Form 8-K, convertible notes, May 14, 2026. https://www.sec.gov/Archives/edgar/data/1878848/000114036126021285/ef20073507_8k.htm
- IREN, Form 8-K, senior secured notes, May 29, 2026. https://www.sec.gov/Archives/edgar/data/1878848/000114036126023427/ef20075181_8k.htm
- Lambda, announcement of $1 billion senior secured credit facility, May 2026. https://lambda.ai/blog/lambda-closes-1-billion-senior-secured-credit-facility
- IFR, Blue Owl Capital/Beignet Investor $27.3 billion 23.6-year bond. https://www.ifre.com/ifr-awards/2327933/financing-package-blue-owl-capitalbeignet-investors-us27.3bn-23.6-year-bond
- Meta, press release on joint venture with Blue Owl Capital for Hyperion data center, Oct. 21, 2025. https://about.fb.com/news/2025/10/meta-blue-owl-capital-develop-hyperion-data-center/
- Nebius, Form 6-K, convertible notes, June 2, 2025. https://www.sec.gov/Archives/edgar/data/1513845/000110465925055197/tm2516825d1_6k.htm
- Nebius, Form 6-K, convertible notes, Sept. 15, 2025. https://www.sec.gov/Archives/edgar/data/1513845/000110465925089969/tm2525580d4_6k.htm
- Nebius, Form 6-K, convertible notes, Mar. 20, 2026. https://www.sec.gov/Archives/edgar/data/1513845/000110465926032735/tm268409d4_6k.htm
- Nebius, Form 6-K, term loan, July 17, 2026. https://www.sec.gov/Archives/edgar/data/1513845/000110465926084452/tm2620683d1_6k.htm
- Nebius, Form 6-K, convertible notes, Aug. 24, 2026. https://www.sec.gov/Archives/edgar/data/1513845/000110465926100347/tm2623863d1_6k.htm
- TeraWulf, Form 8-K, convertible notes, Aug. 20, 2025. https://www.sec.gov/Archives/edgar/data/1083301/000110465925080911/tm2523651d5_8k.htm
- TeraWulf, Form 8-K, convertible notes, Aug. 20, 2025. https://www.sec.gov/Archives/edgar/data/1083301/000110465925081886/tm2523651d6_8k.htm
- TeraWulf, Form 8-K, senior secured notes, Oct. 23, 2025. https://www.sec.gov/Archives/edgar/data/1083301/000110465925101866/tm2529300d1_8k.htm
- TeraWulf, Form 8-K, convertible notes, Oct. 31, 2025. https://www.sec.gov/Archives/edgar/data/1083301/000110465925104928/tm2529894d1_8k.htm
- TeraWulf, Form 8-K, senior secured notes, Dec. 29, 2025. https://www.sec.gov/Archives/edgar/data/1083301/000110465925124839/tm2534384d1_8k.htm
- TeraWulf, Form 8-K, term loan, Mar. 13, 2026. https://www.sec.gov/Archives/edgar/data/1083301/000095014226000720/eh260751501_8k.htm
- Vantage Data Centers, press release on $5 billion in incremental green loan financings, June 2025. https://vantage-dc.com/news/vantage-data-centers-secures-5b-in-incremental-green-loan-financings-to-support-demand-for-north-america-platform/
- Vantage Data Centers, press release on $2 billion credit facility, Sept. 2026. https://vantage-dc.com/news/vantage-secures-2b-credit-facility-expanding-financing-to-support-growing-demand/
- SpaceX, 424B4 prospectus (xAI debt, Note 10), June 2026. https://www.sec.gov/Archives/edgar/data/1181412/000162828026042639/spaceexplorationtechnologi.htm
- Alphabet, 424B2 prospectus supplement, senior unsecured notes, Apr. 28, 2025. https://www.sec.gov/Archives/edgar/data/1652044/000119312525107005/d910841d424b2.htm
- Alphabet, 424B2 prospectus supplement, senior unsecured notes, Apr. 29, 2025. https://www.sec.gov/Archives/edgar/data/1652044/000119312525110061/d926856d424b2.htm
- Alphabet, 424B2 prospectus supplement, senior unsecured notes, Nov. 3, 2025. https://www.sec.gov/Archives/edgar/data/1652044/000119312525267244/d64361d424b2.htm
- Alphabet, 424B2 prospectus supplement, senior unsecured notes, Nov. 3, 2025. https://www.sec.gov/Archives/edgar/data/1652044/000119312525267232/d65573d424b2.htm
- Alphabet, 424B2 prospectus supplement, senior unsecured notes, Feb. 9, 2026. https://www.sec.gov/Archives/edgar/data/1652044/000119312526046846/d108033d424b2.htm
- Alphabet, 424B2 prospectus supplement, senior unsecured notes, Feb. 10, 2026. https://www.sec.gov/Archives/edgar/data/1652044/000119312526048730/d108423d424b2.htm
- Alphabet, 424B2 prospectus supplement, senior unsecured notes, May 5, 2026. https://www.sec.gov/Archives/edgar/data/1652044/000119312526212222/d325417d424b2.htm
- Alphabet, 424B2 prospectus supplement, senior unsecured notes, May 5, 2026. https://www.sec.gov/Archives/edgar/data/1652044/000119312526212210/d152073d424b2.htm
- Alphabet, 424B5 prospectus supplement, senior unsecured notes, May 15, 2026. https://www.sec.gov/Archives/edgar/data/1652044/000119312526228923/d137872d424b5.htm
- Alphabet, 424B2 prospectus supplement, senior unsecured notes, Aug. 6, 2026. https://www.sec.gov/Archives/edgar/data/1652044/000119312526340264/d32286d424b2.htm
- Amazon, 424B5 prospectus supplement, senior unsecured notes, Nov. 17, 2025. https://www.sec.gov/Archives/edgar/data/1018724/000110465925114098/tm2530638-4_424b5.htm
- Amazon, 424B5 prospectus supplement, senior unsecured notes, Mar. 10, 2026. https://www.sec.gov/Archives/edgar/data/1018724/000110465926027125/tm266670-4_424b5.htm
- Amazon, 424B5 prospectus supplement, senior unsecured notes, Mar. 11, 2026. https://www.sec.gov/Archives/edgar/data/1018724/000110465926027669/tm266670-6_424b5.htm
- Amazon, 424B5 prospectus supplement, senior unsecured notes, June 8, 2026. https://www.sec.gov/Archives/edgar/data/1018724/000110465926072332/tm2613616-2_424b5.htm
- Amazon, 424B5 prospectus supplement, senior unsecured notes, July 7, 2026. https://www.sec.gov/Archives/edgar/data/1018724/000110465926081786/tm2619352-2_424b5.htm
- Amazon, 424B5 prospectus supplement, senior unsecured notes, Sept. 9, 2026. https://www.sec.gov/Archives/edgar/data/1018724/000110465926107122/tm2624614-3_424b5.htm
- Meta, 424B2 prospectus supplement, senior unsecured notes, Oct. 30, 2025. https://www.sec.gov/Archives/edgar/data/1326801/000119312525261217/d762778d424b2.htm
- Meta, 424B2 prospectus supplement, senior unsecured notes, Apr. 30, 2026. https://www.sec.gov/Archives/edgar/data/1326801/000119312526201738/d109954d424b2.htm
- Oracle, 424B2 prospectus supplement, senior unsecured notes, Jan. 30, 2025. https://www.sec.gov/Archives/edgar/data/1341439/000119312525018491/d890482d424b2.htm
- Oracle, 424B2 prospectus supplement, senior unsecured notes, Sept. 24, 2025. https://www.sec.gov/Archives/edgar/data/1341439/000119312525217490/d37885d424b2.htm
- Oracle, 424B2 prospectus supplement, senior unsecured notes, Feb. 2, 2026. https://www.sec.gov/Archives/edgar/data/1341439/000119312526035603/d33906d424b2.htm
- SEC EDGAR, Microsoft filing index (no 424B or free writing prospectus filings, January 2025 to October 7, 2026). https://www.sec.gov/cgi-bin/browse-edgar?action=getcompany&CIK=0000789019&type=424&dateb=&owner=include&count=40